 Erection Of A 500Kw Wind Turbine With Height To Tip Of 60M, Height To Hub Of 38M, Hard Standing, Substation & Upgrade Of Existing Access Track
 02 Mar 2015
 Highland Council (14/04171/FUL), Highland Council
 04 Nov 2014
 Failure to give a decision
 Decision
 No remit
 Case Owner, DPEA (Tel: 0300 244 6668 - Email: dpea@gov.scot)
 not applicable
 17 Mar 2015 (No Jurisdiction to consider)
 Wind turbine (single),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 2 of 2
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
02 Mar 2015 04 Mar 2015 Appeal form form - dated 2 March 2015 0.08MB (URL Details)
17 Mar 2015 Decision Notice e-mail to Mr Colin Risbridger - advising no remit to consider - sent 17 March 2015 0.31MB (URL Details)

Click table headers to sort table

  • <<
  • <