PPA-170-2153 (Planning Permission Appeal)
 https://dpea.scotland.gov.uk/CaseDetails.aspx?id=121751
 Land At Margree, St John’S Town Of Dalry, Dumfries And Galloway, DG7 3XJ
 -4.0807844
 55.155249
 586523
 267514
 The Erection, 35 Year Operation And Subsequent Decommissioning Of A Wind Farm Comprising Of Up To 9 Wind Turbines And Associated Development
 9
 200.00
 49.90
 Planning permission
 04 Aug 2021
 Dumfries and Galloway Council (20/2085/FUL)
 04 Dec 2020
 Energiekontor UK Ltd
 Mr George Sismey-Durrant
 Failure to give a decision
 Site Inspection
 Decision
 Decision issued
 Case Owner, DPEA (Tel: 0300 244 6668 - Email: dpea@gov.scot)
 Mr David Buylla
 13 Dec 2021
 21 Mar 2022 (Appeal Allowed )
 Wind Farm (two or more turbines),
 
contains