PPA-130-2064 (Planning Permission Appeal)
https://dpea.scotland.gov.uk/CaseDetails.aspx?id=118390
Clachaig Glen Windfarm, Land North East Of Muasdale, Argyll, PA29 6UZ
641550
172190
Erection Of 14 Wind Turbines (13 With A Blade Tip Height Of Up To 126.5M (And Hub Height Of Up To 80M) And One With A Blade Tip Height Of Up To 115.5M (And Hub Height Of Up To 69M)), Upgrading Of Permanent Access, Formation Of Site Access Tracks, Erection Of Permanent Anemometer Mast, Control Building And Substation, Watercourse Crossings And Temporary Construction Compound.
Planning permission
Argyll and Bute Council (16/01313/PP)
21 Sep 2017
E.ON Climate & Renewables UK
Site Inspection, Further Written Submission, Inquiry, Hearing
03 Jul 2018
18 Dec 2019 (Appeal Allowed )
Wind Farm (two or more turbines),