WIN-140-7 (Section 36 Wind Farm)
 https://dpea.scotland.gov.uk/CaseDetails.aspx?id=118007
 Birneyknowe Wind Farm, Located Approximately 4Km Se Of Hawick And 2 Km West Of Bonchester Bridge, Scottish Borders, TD9
 -2.7192871
 55.393544
 611301
 354537
 Application For Consent Under S36 Of The Electricity Act 1989 And Direction Under S57(2) Of The Town And Country Planning (Scotland) Act 1997 That Planning Permission Is Deemed To Be Granted For The Construction And Operation Of A Wind Farm Known As Birneyknowe Wind Farm
 12 May 2017
 Scottish Borders Council (14/00530/S36)
 Amy Townsend
 Banks Renewables (Birneyknowe Wind Farm) Limited
 Site Inspection, Further Written Submission, Inquiry, Hearing
 Report
 Decision issued
 Case Owner, DPEA (Tel: 0300 244 6668 - Email: dpea@gov.scot)
 Mr David Liddell
 29 Mar 2018 at 11:30
 25 Oct 2017
 22 Dec 2017
 21 Dec 2018 (Application Refused)
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 1 of 1
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
28 Feb 2018 02 Mar 2018 Agenda DPEA Hearing Agendas 0.17MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 1 of 1