TRL-130-1 (Section 37 Transmission line)
 https://dpea.scotland.gov.uk/CaseDetails.aspx?id=122768
 Site Located Between Proposed Creag Dhubh Substation And The Existing Scottish Power Energy Networks, (Spen) 275Kv Overhead Line (Ohl) From Dalmally To Inverarnan, Near Glen Lochy, (Succoth Glen), Argyll & Bute, PA32
 -5.0950896
 56.329226
 719509
 208739
 13.3 Kilometre (Km) Double Circuit 275 Kv Ohl, Supported By 48 Lattice Steel Towers Between A Proposed Substation At Creag Dhubh To The Existing Spen 275 Kv Ohl, Known As The Yw Route, That Runs From Dalmally To Inverarnan, Near Succoth Glen (Glen Lochy);
 14 Nov 2022
 Argyll and Bute Council (N/A)
 Scottish Hydro Electric Tranmission Plc
 Inquiry
 Report
 Decision issued
 Davidson, Rebecca (Tel: 01312448263 - Email: Rebecca.Davidson@gov.scot)
 Mr David Buylla
 10 Feb 2023
 24 Dec 2023
 21 Aug 2024 (Application Granted)
 Substation/Transmission Line/Pipeline,
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 2 of 2
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
21 Aug 2024 21 Aug 2024 Decision Notice ECU Decision Notice - dated 21st of August 2024 5.07MB (URL Details)
23 Nov 2023 21 Aug 2024 Report DPEA Report – dated 23 November 2023 0.75MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 2 of 2