CIN-ORK-002 (Called-in application)
 https://dpea.scotland.gov.uk/CaseDetails.aspx?id=121230
 Lyness (Land Near), Hoy, Orkney,
 Erection Of 6 Wind Turbines (Max Height 149.9 Metres, Max Wind Farm Capacity 50Mw) , Erect A Meteorological Mast (Max Height 90 M), With A Total Generating Capacity For The Site Would Be Approximately 28.8Mw, And A Substation, Construct Access Tracks, A Water Crossing And Underground Cabling, Create A Borrow Pit, And Associated Infrastructure
 19 Oct 2020
 Orkney Islands Council (20/313/TPPMAJ)
 Ms Jenny Hazzard
 Orkney Islands Council
 Site Inspection
 Report
 Court of Session Decision Issued
 Ramsay, Elaine (Tel: 0131 244 7538 - Email: Planning.Decisions@gov.scot)
 Mr David Buylla
 05 Jul 2021
 21 Dec 2021 (Application Granted)
 Upheld
 05 Oct 2022
 Wind Farm (two or more turbines),
 
The decision for this case remains on the web site because the decision issued by DPEA has not been overturned, and judgements can be found on Court of Session’s website.
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 2 of 2
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
25 May 2021 23 Nov 2022 Representation Ironside Farrar Peat Landslide Hazard Risk Assesment - Stage 1 Checking Report 0.59MB (URL Details)
18 Nov 2020 23 Nov 2022 Representation Interested party Leitch, James & Nina 0.09MB (URL Details)