CPO-210-2 (Compulsory Purchase Order)
 https://dpea.scotland.gov.uk/CaseDetails.aspx?id=123512
 The Berwick Bank Wind Farm, Lands Between Skateraw And Branxton, East Lothian, EH42 1QT
 -2.4183789
 55.959334
 674114
 373977
 The Berwick Bank Wind Farm (Onshore Works) Compulsory Purchase Order 2023 - Acquire The Necessary Rights And Land To Construct, Operate And Remove Electricity Transmission Lines, Plant And Ancillary Infrastructure Between Mean Low Water Springs At Skateraw And The National Electricity Transmission System (Or "Grid") Connection Point At Branxton
 26 Apr 2023
 East Lothian Council (N/A)
 Mr Colin Hamilton
 Site Inspection, Inquiry, Hearing
 Report
 Report Issued
 Anderson, Jayne (Tel: 0131 244 6934 - Email: jayne.anderson@gov.scot)
 Mr Paul Cackette
 28 Aug 2023 at 11am
 16 Nov 2023
 11 Jan 2024
 **Case Update – 16/05/2024** A report for this case has been submitted to Scottish Ministers. A decision by Scottish Ministers will be made in due course.
 Compulsory Purchase Order ,
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 1 of 1
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
11 Oct 2023 30 Oct 2023 Representation Bell Rural Solutions obo David and Caroline Cricht Request to withdraw 0.14MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>