TRL-170-4 (Section 37 Transmission line)
 https://dpea.scotland.gov.uk/CaseDetails.aspx?id=122047
 Kendoon To Tongland 132Kv Reinforcement (Ktr) Project, Glenlee To Tongland , Located Approximately 1 Km South West Of St John’S Town Of Dalry, DG6 4LT
 -4.0351034
 54.860646
 553660
 269470
 Consent Under S37 Of The Electricity Act 1989 And Deemed Planning Permission Under S57(2) Of The Town And Country Planning (Scotland) Act 1997 To Install And Keep Installed Overhead Electric Lines Described Collectively As The Kendoon To Tongland Reinforcement Project In Dumfries And Galloway Planning Authority Area
 01 Feb 2022
 Dumfries and Galloway Council (N/A)
 Ms Magdalena MacLean
 SP ENergy Networks
 Site Inspection, Further Written Submission, Inquiry, Hearing
 Report
 Report Issued
 Bell, Colin (Tel: 0131 244 6902 - Email: colin.bell@gov.scot)
 Ms Katrina Rice
 Mr David Buylla
 30 Nov 2022 at 9:00
 15 Jun 2022
 20 Mar 2023
 **Case Update – 07/02/2024** A report for this case has been submitted to Scottish Ministers. A decision by Scottish Ministers will be made in due course.
 Substation/Transmission Line/Pipeline,
 
contains

  • <<
  • <
  • 1
  • 2
  • 3
  • 4
  • >
  • >>
  • Displaying Results 0 - 10 of 39
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
10 Aug 2022 10 Aug 2022 Note of Meeting DPEA Annex 1 and 2 of PEM note following FWS - Update 10 August 2022 0.11MB (URL Details)
10 Aug 2022 24 Aug 2022 Note of Meeting DPEA Annex 1 and 2 of PEM note following FWS - Update 10 August 2022 0.11MB (URL Details)
21 Jul 2022 24 Aug 2022 Response Agent - Shepherd & Wedderburn LLP Response to PEM Note - Further Comments - Biodiversity Officer related matters 0.29MB (URL Details)
15 Jul 2022 24 Aug 2022 Response Harper Macleod LLP - for Authority Response to PEM Note - Biodiversity Consultation Response - 4 July 2017 2 0.27MB (URL Details)
14 Jul 2022 24 Aug 2022 Response Agent - Shepherd & Wedderburn LLP Response to PEM Note - Suggested itinerary for site inspection - Master Map_A1 12.93MB (URL Details)
13 Jul 2022 24 Aug 2022 Response Agent - Shepherd & Wedderburn LLP Response to PEM Note - Suggested itinerary for site inspection - excluding confidential Table 2 - updated 15 July 2022 0.45MB (URL Details)
12 Jul 2022 24 Aug 2022 Response Authority - Harper Macleod LLP Response to PEM Note - consultation response as referred to in committee report -Council_Archaeologist-1041861 - TRL-170-4 0.15MB (URL Details)
12 Jul 2022 24 Aug 2022 Response Authority - Harper Macleod LLP Response to PEM Note - consultation response as referred to in committee report - Council Landscape Architect (composite response) - ALL TRL 0.69MB (URL Details)
12 Jul 2022 24 Aug 2022 Response Authority - Harper Macleod LLP Response to PEM Note - consultation response as referred to in committee report - Council_Access_Officer (Composite response) - ALL TRL 2.55MB (URL Details)
12 Jul 2022 24 Aug 2022 Response Authority - Harper Macleod LLP Response to PEM Note - consultation response as referred to in committee report - Council_Access_Officer-plan 1 showing core paths and rights of way (composite) - ALL TRL 0.66MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • 2
  • 3
  • 4
  • >
  • >>
  • Displaying Results 0 - 10 of 39