TRL-170-3 (Section 37 Transmission line)
https://dpea.scotland.gov.uk/CaseDetails.aspx?id=122046
Kendoon To Tongland 132Kv Reinforcement (Ktr) Project – Earlstoun To Glenlee, Approximately 1Km North And 1Km South West Of, St John’S Town Of Dalry, DG7 3SR
581900
261410
Consent Under S37 Of The Electricity Act 1989 And Deemed Planning Permission Under S57(2) Of The Town And Country Planning (Scotland) Act 1997 To Install And Keep Installed Overhead Electric Lines Described Collectively As The Kendoon To Tongland Reinforcement Project In Dumfries And Galloway Planning Authority Area
Dumfries and Galloway Council (N/A)
Site Inspection, Further Written Submission, Inquiry, Hearing
**Case Update – 07/02/2024**
A report for this case has been submitted to Scottish Ministers. A decision by Scottish Ministers will be made in due course.
Substation/Transmission Line/Pipeline,